Is the amount of time an activity can be delayed without delaying succeeding activity?

by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات
5 years ago

Show

 

Thank you for the invitation

 Option B. A&C

Free float is the amount of time an activity can be delayed without affecting the start time of the succeeding activity.

That is right answer

not 

Option B. C&B

by يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء
5 years ago

Thank you for the invitation I agree the answer b

by Abdul Rehman , Electrical Engineer , Al Toufeer Construction & General Maintenance LLC
5 years ago

Thanks for the invitation. My answer is C

Thank you for invitation. I seem B. c and b is good answer.

Is the amount of time an activity can be delayed without delaying succeeding activity?

The answer is C.

There are 2 concepts need to be clarified. Float and Total Float.

Float is the amount of time that an activity can be delayed from its early start without delaying the successor activity.

Total Float is the amount of time that an activity can be delayed from its early start without delaying the project end date.

To get more information on Project Management, follow the following page:

https://www.facebook.com/ProjectLife-1112296792185437

Appreciation for the invitation. It is option A - Float.

by Ayoub Tartir , PMP, GWCPgM, CISA, CISSP, CAP, CSSLP, FITSP-D, CEH, CHFI, CCNA, CCNA Security, Security+, Network+ , IT Security Expert , Information Unlimited Inc. (IUI)
5 years ago

My answer is for option (A)

In my opinion - B. c and b

by Muhammad Asif , Relationship Officer OG II , FAYSAL BANK LTD
2 months ago

Based on the given network, what is the sum of floats of activities A, B and C (Floats A+B+C) ?

by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)
5 years ago

Of course it is C - Total Float .

Popular Searches

Table of Contents

Nội dung chính Show

  • What is the name of the amount of time an activity may be delayed from its earliest start without delaying the finish of the project?
  • Which of the following is the maximum amount of time an activity can be delayed from its early start without delaying the entire project?
  • Is the amount of time an activity can be delayed without delaying the?
  • Is the amount of time an activity can be delayed without delaying the project?
  • What is the amount of time that a schedule activity can be delayed without delaying the early start of any successor activity or violating a schedule constraint?
  • Is critical path the longest?
  • Why is activity 2.2.3 delayed by 2 days?
  • Is the amount of time an activity can be delayed from its early start without delaying the planned?
  • What is the duration by which an activity can be delayed without delaying the project?
  • Is the amount of time that an activity can be delayed before it impacts the project's planned completion?
  • Is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date?
  • What do you call the amount of time that a scheduled activity can be delayed without delaying the early start of any immediately following activity?
  • What is the amount of time that a task can be delayed without affecting the subsequent tasks?
  • Is the amount of time by which the completion of activity can be delayed without affecting the final project duration?

  • What is the name of the amount of time an activity may be delayed from its earliest start without delaying the finish of the project?
  • Which of the following is the maximum amount of time an activity can be delayed from its early start without delaying the entire project?
  • Is the amount of time an activity can be delayed without delaying the?
  • Is the amount of time an activity can be delayed without delaying the project?
  • What is the amount of time that a schedule activity can be delayed without delaying the early start of any successor activity or violating a schedule constraint?
  • Is critical path the longest?
  • Why is activity 2.2.3 delayed by 2 days?
  • Is the amount of time an activity can be delayed from its early start without delaying the planned?
  • What is the duration by which an activity can be delayed without delaying the project?
  • Is the amount of time that an activity can be delayed before it impacts the project's planned completion?
  • What term is used for the amount of time an activity can be delayed?
  • What is the name of the amount of time an activity may be delayed from its earliest start without delaying the finish of the project?
  • Which of the following is the maximum amount of time an activity can be delayed from its early start without delaying the entire project?
  • Is the amount of time an activity can be delayed without delaying the?
  • Is the amount of time an activity can be delayed without delaying the project?
  • What is the amount of time that a schedule activity can be delayed without delaying the early start of any successor activity or violating a schedule constraint?
  • What is the amount of time an activity can be delayed without deleting a succeed in activity or project finish date?
  • Is critical path the longest?
  • Why is activity 2.2.3 delayed by 2 days?
  • How are starting dates assigned to an activity?

Total float
The amount of time that an activity can be delayed from its early start without delaying the project finish date. Total float is a mathematical calculation and can change as the project progresses and changes are made to the project plan. Also called “float,” “slack,” and “path float.” See also free float.

What is the name of the amount of time an activity may be delayed from its earliest start without delaying the finish of the project?

Interfering Float is the amount of time a schedule activity can be delayed or extended from its early start date without delaying the project finish date. However, it should be understood that delaying an activity into interfering float will delay the start of one or more following non-critical activities.

Is the amount of time an activity can be delayed without impacting the early start date of its successor?

Free float: It is the amount of time that the activity completion time can be delayed without affecting the earliest start time of the immediate successor activities in the network.

Which of the following is the maximum amount of time an activity can be delayed from its early start without delaying the entire project?

Slack
Slack is the amount of time that an activity can be delayed past its earliest start or earliest finish without delaying the project. The critical path is the path through the project network in which none of the activities have slack, that is, the path for which ES=LS and EF=LF for all activities in the path. 4.

Is the amount of time an activity can be delayed without delaying the?

So, A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date.

What term defines the amount of time an activity can be delayed and not delay the project?

The term total slack refers to the amount of time an activity can be delayed without delaying the start of a subsequent activity. The term Late Finish refers to the latest time an activity may begin without delaying the completion of the project.

Is the amount of time an activity can be delayed without delaying the project?

Total Float (TF) It is the amount of time by which an activity can be delayed without delaying the project duration.

What is the amount of time that a schedule activity can be delayed without delaying the early start of any successor activity or violating a schedule constraint?

Total Float is the amount of time a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. The Total Float (also referred to as just float or slack) of any activity on the Critical Path is usually 0 (zero).

What is the amount of time an activity can be delayed without delaying succeeding activity or project finish date?

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.

Solution(By Examveda Team) Free Float is the amount of time that an activity can be delayed without delaying the early start date of any successor activity.

Is critical path the longest?

The critical path (or paths) is the longest path (in time) from Start to Finish; it indicates the minimum time necessary to complete the entire project.

How much can C be delayed without delaying the project?

Can activity C be delayed without delaying the entire project? If so, by how many weeks? Yes, C can be delayed by 2 weeks.

Why is activity 2.2.3 delayed by 2 days?

Observe that John is willing to work on weekends, but activity 2.2.3 is delayed by two days because one of the moving companies did not provide bids on the weekend. Observe that activity 2.3 has a lead time of one day, but that relationship is between activity 2.1 and 2.3.

Starting dates can be assigned to each activity by doing a forward pass proceeding from left to right in the network diagram beginning with the project start date. The dates derived by this method are the early start (ES) dates. The early start date for an activity is the earliest date the activity can begin.

When to assign the calculated date to the late start date?

Assign the calculated date as the late start date of the predecessor activity. The difference between the early start date and the late start date for activities on the critical path is usually the same as the total float, unless the activities are affected by the resource calendars differently in the forward and backward pass.

Is the amount of time an activity can be delayed from its early start without delaying the planned?

FloatThe amount of time an activity can be delayed from an early start without delaying the completion date., sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

15. When developing a project schedule, total float refers to the amount of time a schedule activity may be delayed from its early start date without delaying the project end date.

What is the duration by which an activity can be delayed without delaying the project?

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float") project completion date ("total float").

Is the amount of time that an activity can be delayed before it impacts the project's planned completion?

Total slack is the amount of time a task can be delayed before the project finish date is delayed. Total slack can be positive or negative. A positive slack indicates the amount of time that the task can be delayed without delaying the project finish date.

The answer is C.

There are 2 concepts need to be clarified. Float and Total Float.

Float is the amount of time that an activity can be delayed from its early start without delaying the successor activity.

Total Float is the amount of time that an activity can be delayed from its early start without delaying the project end date.

To get more information on Project Management, follow the following page:

https://www.facebook.com/ProjectLife-1112296792185437

Is the total amount of time that a schedule activity may be delayed from its early start date without delaying the project finish date?

Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

What do you call the amount of time that a scheduled activity can be delayed without delaying the early start of any immediately following activity?

Free float is an amount of time that a schedule activity can be delayed without delaying the early start of any immediately following schedule activities.

What is the amount of time that a task can be delayed without affecting the subsequent tasks?

So, A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.

Is the amount of time by which the completion of activity can be delayed without affecting the final project duration?

Total float: It is the amount of time that the completion time of an activity can be delayed without affecting project completion time.

Which is the amount of time an activity can be delayed?

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.

Is the amount of time a schedule activity can be delayed without delaying the early start of any successor?

Free Float, per definition, is the amount of time that the activity can be delayed before any successors will be delayed. Early Start/Finish times are used to calculate the Free Float values.

Is the amount of time an activity can be delayed without taking away float from later activities?

Total float is how long an activity can be delayed without putting off the project completion date. On a critical path, the total float is zero. Total float is often known as the slack. You can calculate it by subtracting the Early Start date of the activity from its Late Start Date.